| 905(b)s |
||
|
·
Each district should have a
generic QCP o
sample schedule |
||
· Mandatory Milestone: Preview Study Findings held prior to submittal to Division for approval
o
PDT
o
Discuss outstanding issues or potential
policy questions
o
The memorandum summarizing the conference shall be signed by the
planning function chief within 10 days of the conference and distributed to all
participants
·
ITR: One person “expert” reviewer
documents results of technical review
·
PMP and FCSA: Feasibility Scope,
schedule and costs including work-in kind
·
Certification by District Planning Chief
·
Submitted via e-mail to Division’s
planning district support team member
·
Policy Review
o
Planning manager leads policy review and
documents--comments, responses, discussions, and required actions—in policy
compliance memorandum
o
Policy Compliance Memorandum Comments
provided within two weeks
o
Planning program manager approves 905(b)
via e-mail, including HQ RIT providing them the approved 905(b) and policy
compliance memorandum.