WBS Level WBS /Activity Activity Name Milestone - SPL Milestone - Civil Works WCC (CEFMS) - Civil Works
        1 Civil Works Standard Project Name      
        2   22000  Feasibility Study      
        3  22000.22T00  Feasibility Study Program & Project Management        
        5 1010 Initiate Feasibility Study (F1) 100 CW140 22T0*
        5 1020 Conduct Program and Project Management     22T0*
        5 1030 Feasibility Study Travel     22T0*
        5 1040 Feasibility Study Technical Management     22T0*
        5 1050 Feasibility Study Close Out     22T0*
        3  22000.22A00  Public Involvement        
        5 2000 Initial Public Meeting Preparation     22A0*
        5 2010 Public Workshop/Scoping Meeting (F2) 101   22A0*
        5 2020 Public Workshop in support plan selection     22A0*
        5 2030 Feasibility Public Review Period Start 145 CW250 22A0*
        5 2040 Feasibility Public Review Period     22A0*
        5 2050 Prepare Final Public Meeting     22A0*
        5 2060 Final Public Meeting (F6) 162   22A0*
        3  22000.22S00  Feasibility Report Preparation        
        5 3000 Study Management     22Q0*
        5 3010 Plan Formulation and Evaluation     22R0*
        5 3020 Report Preparation-Pre-P2     22S0*
        5 3030 Report Preparation-W/o Project Condition &Preliminary Plan (F3)     22S0*
        5 3040 Technical Review-W/o Project Condition &Preliminary Plan (F3)     22R0*
        5 3050 Feasibility Scoping Meeting (F3) 102   22S0*
        5 3060 Report Preparation- With Project Conditions & Preliminary Recommended Plan (F4)     22S0*
        5 3070 Technical Review-With Project Conditions & Preliminary Recommended Plan (F4)     22S0*
        5 3080 Alternative Review Conference (F4) 103   22S0*
        5 3090 Report Preparation AFB Report     22S0*
        5 3100 Technical Review-AFB     22S0*
        5 3110 Send AFB Package to SPD DST RIT     22S0*
        5 3120 Alternative Formulation Briefing (F4A) 124 CW190 22S0*
        5 3130 Feasibility Project Guidance Memo (PGM)   CW060 22S0*
        5 3140 Report Preparation-Draft Report     22S0*
        5 3150 Tecnical Review-Draft Report     22S0*
        5 3160 Draft Feasibility Report (F5)   CW150 22S0*
        5 3170 Feasibility Review Conference (FRC) (F7) 130 CW050 22S0*
        5 3180 Report Preparation-Final Report     22S0*
        5 3190 Technical Review-Final Report     22S0*
        5 3200 Final Report to SPD (F8) 165 CW160 22S0*
        5 3210 SPD DST Review and Preparation of DE's Notice     22S0*
        5 3220 MSC Commander's Public Notice (F9) 170 CW260 22S0*
        5 3230 Feasibility Report Approval   CW170 22S0*
        5 3240 Feas State/Agency Reivew     22S0*
        5 3250 Coastal Zone Management (CZM) Compliance Received   CW240 22S0*
        5 3260 401 State Water Quality Certification   CW220 22S0*
        5 3270 SPD RIT Review and Preparation of Chief's Report     22S0*
        5 3280 Record of Decision(ROD) Signed 320 CW230 22S0*
        5 3290 Chief's Report 330 CW270 22S0*
        5 3300 ASA (CW) Memo to OMB   CW280 22S0*
        5 3310 Feasibility Report to Congress via OMB 340 CW180 22S0*
        5 3320 Project Authorization 350   22S0*
        3  22000.22E00  Environmental Impact Statement        
        4  22000.22E00.22E001  Environmental Studies        
        5 4000 ENV-W/o Project Conditions & Preliminary Plan (F3)     22E0*
        5 4010 ENV-With Project Conditions for Final Plan (F4)     22E0*
        5 4020 ENV-Draft Environmental Impact Statement (F5)     22E0*
        5 4030 ENV-Final Environmental Impact Statement (F*)     22E0*
        5 4040 Feasibility EIS Complete   CW210 22E0*
        4  22000.22E00.22E002  Biology Studies        
        5 4100 BIO-Without Project Conditions and Preliminary Analysis (F3)     22E0*
        5 4110 BIO-With Prodject Conditions for Final Plan (F4)     22E0*
        5 4120 BIO-Draft EIS/EA     22E0*
        5 4130 BIO-Final Report     22E0*
        4  22000.22E00.22D00  Cultural Resources        
        5 4200 Cultural-Without Project Conditions and Preliminary  Plan (F3)     22D0*
        5 4210 Cultural- With Project Conditions for Final Plans (F4)     22D0*
        5 4220 Cultural- Draft EIS/EA     22D0*
        5 4230 Cultural-Final Report     22D0*
        4  22000.22E00.22F00  F&W Coordination        
        5 4300 Planning Aid Report(s), HEP participation, other coordination (F3)     22F0*
        5 4310 Planning Aid Report(s), HEP participation, other coordination (F4)     22F0*
        5 4320 Coordination Act Report     22F0*
        3  22000.22P00  Engineering Appendix        
        4  22000.22P00.22J00  Hydrology & Hydraulics Studies Appendix        
        5 5000 H&H-Without Project Conditions and Preliminary  Plan (F3)     22J0*
        5 5010 H&H-With Project Conditions for Final Plans (F4)     22J0*
        5 5020 H&H-Draft Report (F5)     22J0*
        5 5030 H&H- Final Report     22J0*
        4  22000.22P00.22K00  Geotechnical Studies Appendix        
        5 5100 Geotech-Without Project Conditions and Preliminary  Plan (F3)     22K0*
        5 5110 Geotech-With Project Conditions for Final Plans (F4)     22K0*
        5 5120 Geotech-Draft Report (F5)     22K0*
        5 5130 Geotech- Final Report     22K0*
        4  22000.22P00.22L00  HTRW Studies Appendix        
        5 5200 HTRW-Without Project Conditions and Preliminary  Plan (F3)     22L0*
        5 5210 HTRW-With Project Conditions for Final Plans (F4)     22L0*
        5 5220 HTRW-Draft Report (F5)     22L0*
        5 5230 HTRW-Final Report     22L0*
        4  22000.22P00.22P001  Engineering Analysis and Design Appendix        
        5 5300 Surveys and Mapping     22N0*
        5 5310 E&D-Without Project Conditions and Preliminary  Plan (F3)     22P0*
        5 5320 E&D-With Project Conditions for Final Plans (F4)     22P0*
        5 5330 E&D-Draft Report (F5)     22P0*
        5 5340 E&D- Final Report     22P0*
        4  22000.22P00.22P002  Project Cost Estimate Appendix        
        5 5400 Cost Engineering-Without Project Conditions and Preliminary  Plan (F3)     22P0*
        5 5410 Cost Engineering-With Project Conditions for Final Plans (F4)     22P0*
        5 5420 Cost Engineering-Draft Report(F5)     22P0*
        5 5430 Cost Engineering- Final Report     22P0*
        3  22000.22H00  Real Estate Appendix        
        5 6000 RE - Without Project Conditions and Preliminary  Plan (F3)     22H0*
        5 6010 RE - With Project Conditions for Final Plans (F4)     22H0*
        5 6020 RE - Draft Report (F5)     22H0*
        5 6030 RE - Final Plan     22H0*
        3  22000.22G00  Economics/Sociology Appendix        
        5 7000 Economics/Sociology - W/o Project Conditions & Preliminary Plan (F3)     22G0*
        5 7010 Economics/Sociology - With Project Conditions for Final Plans(F4)     22G0*
        5 7020 Economics/Sociology - Draft Report     22G0*
        5 7030 Economics/Sociology - Final Report     22G0*
        3  22000.22P00  Value Engineering Study        
        5 8000 Conduct Value Engineering Study Study (if expected project cost exceeds $10M)     22P0*
        3  22000.00500  PED Phase Project Management Plan        
        5 9000 Start PED PMP   CW030 500
        5 9010 Complete Draft PMP     500
        5 9020 Review e-PMP     500
        5 9030 PED PMP Approval 160 CW040 500
        3  22000.22T00  Design Agreement        
        5 10000 Start Design Agreement   CW070 22T0*
        5 10010 Prepare Design Agreement     22T0*
        5 10020 Submit Design Agreement (if deviations from the model)     22T0*
        5 10030 MSC Approves Design Agreement (if deviations from the model)     22T0*
        5 10040 HQ Approves Design Agreement (if deviations from the model)     22T0*
        5 10050 Local Sponsor Signs Design Agreement     22T0*
      5 10060 Design Agreement  Executed 290 CW130 22T0*