CECW-PM
21 February 2002
Transmittal Memo
Bolinas
Lagoon Ecosystem Restoration Feasibility Study
Alternative Formulation Briefing
Guidance Memorandum
Table of Contents of Issues/Comments
Incremental Cost Analysis
Seadrift Lagoon Component
Historical and Projected Volumes and Habitats
Disposal Costs at Hamilton Airfield Wetland Restoration
Site
Relationship between Hamilton Airfield restoration and the Bolinas Lagoon
Restoration Projects
Least Cost Disposal Site
Operation and Maintenance (O&M) dredging
One Time Dredging Effort
50-Year Habitat Projection
1.
Policy Review Concerns.
Comment:
a. Project Benefits.
The district has used intertidal volume (of water column), measured in cubic yards,
as the parameter by which to measure the environmental outputs (benefits) of the project. While this may be a convenient parameter to use to
conduct cost effectiveness and incremental cost analyses, it does not immediately
translate into any sense of increased habitat for any given species population, or guild
of species, of those animals that are important in the Bolinas Lagoon ecosystem. There is no sense of increased quality of habitat
that comes with just increasing the amount of intertidal volume of water. Consequently, reviewers of the report will not
have a sense of the real benefits to the ecosystem that is being provided by the various
alternatives, with and without the proposed action.
The district should provide a concomitant assessment of the habitat gains expected
with the increase in intertidal volume for each of the alternatives considered and the
species of animals that will be benefited and how much they will be benefited. The habitat unit (HU), as derived from
the Habitat Evaluation Procedures instituted by the U.S. Fish and Wildlife Service, or
other similar science-based habitat evaluation metric, should be the index of expression
for such habitat gains and be provided for a sufficient number of species populations to
show the breadth and extent of habitat improvements at Bolinas Lagoon. Guidance on measurements of environmental benefits
can be found in ER 1105-2-100, paragraph C-3d(5). Statements
in the AFB materials such as
the Habitat Evaluation Expert Panel
were
unable to justify ranking any of the alternatives above any of the others using the
ecological criteria do not provide sufficient assurances that the expenditure of
approximately $54 million dollars of public monies is justified.
District Response:
The feasibility study evaluated an array of alternatives that would increase the
tidal prism, enlarge the volume of water in the lagoon, and retard the successional
processes that have been converting the lagoon to dry land.
While the action alternatives would certainly achieve the physical outputs of
improved water quality and sediment flux, these structural components are not, per se,
ecological benefits. Since the restoration alternatives will bring the lagoon bathymetry
back to a historical condition (around the 1950s), we expect to see an increase in
the species that are dependent on lower intertidal and subtidal habitat, which have
decreased in number as the lagoon has become shallower.
Using available historical data, the District will assess resource losses and
losses in tidal volume, tying in the goals of the restoration effort to the restoration
benefits that are expected to occur with increases in tidal volume and acreages. This data, along with information on the historic
utilization of the lagoon complex by fish and wildlife resources, will be used to evaluate
the positive correlation between intertidal volumes and habitat output benefits.
Along with the physical changes of the lagoon, stakeholders have observed a decline in the numbers of migratory waterfowl using the lagoon. Wild populations vary in size over time and space making it difficult to quantify trends in abundance with census data from any one location. However, coastal lagoons like Bolinas provide very significant feeding and resting habitat for birds that use shallow water habitat, and the conversion of shallow water habitat to mudflat or upland could have a significant adverse impact on waterfowl. As seen in the table below, there has been a 53% reduction in shallow water habitat suitable for diving waterfowl between 1968 and 1998. Project alternatives have the potential to make a substantial increase in this type of habitat.
To
illustrate the benefit to the diving waterfowl guild of birds, a brief habitat evaluation
has been prepared. This habitat metric is derived from: Habitat Suitability Index Models: Lesser Scaup
(Wintering) U.S. DOI FWS Biological Report 82(10.91) April 1985. This model was
selected because the numbers of scaup observed at Bolinas Lagoon has decreased in recent
time, and because the variables in the model can be used to assess estuarine habitat. The model contains four variables: percent
area with clams, percent area with emergent vegetation, human disturbance of feeding, and
mean water depth. For the scaup, the minimal emergent vegetation and low human disturbance
are optimal. The lagoon currently has roughly
50 acres of habitat that would be optimal feeding depth (1- 3m) and would be populated
with clams.
The NER [North, Central (Riparian) and South (No Seadrift)] would increase optimal feeding habitat to a total of 186 acres, a three to four fold increase.
Surface
Area and Volume Between Depth of 1m to 3m below MSL (-2.70' and 8.70' NGVD) |
||
|
Surface
Area |
Volume |
Summary |
Acres |
Yds3 |
1968 |
95.64 |
379,986 |
1998 |
51.65 |
292,876 |
North,
Central (Estuarine), and South (Seadrift) |
214.36 |
612,675 |
North,
Central (Riparian), and South (Seadrift) |
214.36 |
612,707 |
North,
Central (Estuarine), and South (No Seadrift) |
185.77 |
530,926 |
North,
Central (Riparian), and South (No Seadrift) |
185.77 |
530,958 |
North
and South (Seadrift) |
202.31 |
575,252 |
Indeed, there is a link between the hydrology and the ecology of Bolinas Lagoon; that is, there are ecological benefits associated with the increase of tidal prism. This relationship is explained generally on page four, paragraph two of the AFB information package as follows:
A decrease in tidal prism results
in a loss of subtidal and intertidal habitats, equating to significant changes in habitat
conditions for the species that are dependent on those areas. A decline in subtidal habitat, for example, would
result in the loss of estuarine plants (e.g., eelgrass), invertebrates and fish species in
the lagoon (MCOSD 1996). Steelhead and Coho
salmon are two federally listed Threatened species that would be detrimentally affected by
a loss of subtidal habitat (and access to the watersheds tributaries). Bird diversity would also be affected. Bird surveys indicate that since 1972, diving
birds (e.g., grebes and diving ducks) have decreased, giving rise to birds dependent on
the intertidal zone, such as shorebirds and dabbling ducks.
This trend is counter to statewide and regional trends. These trends will only continue as long as
sediment continues to fill the lagoon. The
next transitional phase to occur would be that of intertidal habitat to upland habitat. According to the Bolinas Lagoon Management Plan
Update (1996), By 2008, the Lagoon will likely be a significantly less valuable
migration and over-wintering location on the Pacific Flyway, where estuarine habitats have
already suffered huge losses and degradation. Other
species, like the harbor seals that use Bolinas Lagoon during their pupping season, would
also suffer losses in habitat quality and quantity. Given
the diversity of wildlife species using the lagoon and its proximity to relatively
undisturbed and protected areas, Bolinas Lagoon is a critical element of a unique
ecosystem. Although Bolinas Lagoon currently
provides important habitat to a variety of species, the value of its habitats will
continue to degrade as intertidal and subtidal habitats continue to decline.
The justification for using tidal prism
(i.e. intertidal volume) as an indicator of benefits is explained on page 15 of the same
document. To further explain the link between
the hydrology and the ecology, however, the following topics will be addressed in the
Draft Feasibility Report:
Evaluation of the Alternatives
An Evolution of Possible Parameters
HEP Analysis
The US Fish and
Wildlife Service determined that HEP was not an appropriate analysis to use for Bolinas
Lagoon. HEP can be used for terrestrial
systems and has been adapted for use in wetland areas, but as of yet, there have not been
any HEP models developed for an estuarine lagoon system.
Habitat Units are easy to work with and understand, but unfortunately, a full HEP
analysis was not appropriate in this case.
Numbers of Species
Numbers of
species were also not used as an indicator of project success because of our inability to
predict changes in the system after a given stimulus, as well as our inability to decipher
(due to a lack of historical ecological data and natural fluctuations in wildlife
populations) short term and long-term changes in the lagoon. That is, we would not be able to come up with an
accurate number of population increase for any particular species because of larger,
regional trends in those species or other factors unrelated to Bolinas Lagoon. In addition, because this kind of project has not
been conducted before, it would be impractical to predict the exact outcome for any
particular species. Using numbers of species
as an indicator of project success would yield results with a high degree of uncertainty.
The Habitat Evaluation Expert Panel
Because of the complexity of Bolinas Lagoon and the link between the hydrology and
the biology, the Bolinas Lagoon Executive Committee decided to convene a panel of experts
hydrologists and biologists familiar with the lagoon to evaluate the
alternatives. Modeled after the expert panel
used in the Everglades project, and supported by the South Pacific Division office, the
Habitat Evaluation Expert Panel (HEEP) would improve the plan formulation process and
evaluate the acceptability and effectiveness of the alternatives. As stated in the HEEP summary report:
Considering
the complexity of the Bolinas Lagoon environment, as well as the interested and concerned
participation of local residents, organizations and agencies, the Bolinas Lagoon Team
(including the Corps and the local sponsor) deemed it prudent to seek the advice of an
expert panel to evaluate each of the proposed project alternatives based on habitat
considerations. By seeking the advice and
consensus of a panel of experts, we hoped to discern the most effective, efficient and
acceptable alternative for accomplishing the objectives of the project. As stated in the Project Study Plan, the
Restoration Goals and Outputs for the Bolinas Lagoon Restoration Project are as follows:
The goal of the
environmental restoration work performed at Bolinas Lagoon is to restore intertidal and
subtidal habitat and stop further loss of these habitats through restoring tidal prism and
improving circulation within the basin, while maintaining key mudflats, marsh vegetation,
and other areas of biological importance. Although
over the long term, sediment deposition will continue to fill the lagoon. This restoration project is intended to
significantly slow the present rate of intertidal and subtidal habitat loss.
Through
many hours of examination and discussion, the Habitat Evaluation Expert Panel has added
integrity and durability to the plan formulation process and the analysis of the proposed
restoration alternatives.
The HEEP succeeded in modifying the
restoration options in order to make them more effective, expressed their concerns for
particular species or groups of species, and determined the hydrological and ecological
benefits of the project. Their analysis
further promoted the project goals as stated in the PSP.
? Red, Yellow, Green Ranking the
Restoration Components
Like in the
Everglades project, the HEEP was originally charged with evaluating the alternatives using
a Red-Yellow-Green evaluation system. Red =
no, or yes only with significant changes; Yellow = concerns exist, but some modification
might appease those concerns; Green = yes. The
panel, however, decided that all of the restoration options were different shades of
Green; none were Yellow or Red. Because of
the significant link between the hydrology and the ecology, the panel decided that any
improvement in the hydrology would bring a concomitant improvement in the ecology. This is especially true because of how the
alternatives were designed to mimic historical conditions in the lagoon. One significant result of this analysis was that
the panel determined that all of the restoration options were environmentally acceptable.
? The Link between Hydrology and
Ecology
Since the
panel was unable to differentiate the alternatives using the Red-Yellow-Green approach,
they were then charged with ranking the alternatives based on their ecological benefit to
the lagoon. It was apparent, however, after
many hours of discussion, that it was impossible to separate the hydrology from the
biology. The panel could establish ecological
criteria, but they were unable to rank the alternatives against those criteria. As a result, the panel decided to list the
ecological and hydrological factors that should be considered when evaluating the
components to see if they could determine a common link between the two that could be used
for the comparison. Looking at the list of
target habitats desired by the panel (ecological factors) and the habitats associated with
improving the hydrology of the system (hydrological factors), the two are clearly linked.
Target Habitats (Ecological):
Shallow subtidal, subtidal, intertidal, eelgrass, terrestrial, riparian or
transition, and tidal nursery habitat
Habitat (Hydraulic): Quantity
(or volume) of intertidal and subtidal habitats
The panel also noted what ecological benefits would arise from an increase in intertidal and subtidal habitats. They assumed, for example, that an increase in subtidal habitat would bring about a benefit to fisheries, diving birds, and foraging seals, as well as potential habitat for eelgrass plants. A benefit to fisheries in the lagoon would also increase the value of the surrounding streams to the fish, creating an overall benefit for this group. These benefits are brought on by improved foraging habitat (due to an improved habitat for prey), improved rearing and nursery habitat, greater potential for escape from predators, and a greater diversification of habitats in the lagoon. The intertidal habitat zone is a source of food for many species higher in the food chain. The mudflats and wetland areas, which serve as habitat for plants and invertebrates, serve as feeding areas and nursery habitats for species higher in the food chain. An increase in intertidal habitat is seen as an overall benefit to the system. Thus, since an increase in intertidal habitat brings about an increase in subtidal habitat, we can assume that the lagoon system would see an overall improvement (improvement in hydrology and biology) if intertidal volume were increased.
After the panel determined that not only could they not separate the biology from the hydrology, but that they were unable to rank the alternatives based on the criteria they had developed (after all, any of the restoration options would provide some level of benefit to the lagoon), the Corps decided that intertidal volume would be an appropriate parameter to use to demonstrate an overall benefit to the lagoon system. When this idea was presented to the expert panel, all of the panel members approved.
Tidal Prism (Intertidal Volume)
The hydrological benefits of using intertidal volume as an indicator of project success is stated in the AFB report on page 15. The hydrological and ecological benefits associated with an increase in intertidal volume have been tied together (above discussion). Their direct link makes intertidal volume an appropriate parameter for evaluating project benefits.
Discussion: It was agreed that the district will
undertake a habitat-based evaluation to quantitatively demonstrate the ecological benefits
associated with implementation of the recommended plan.
The district has indicated that it is prepared to illustrate the benefit to the
diving waterfowl guild of birds using the Habitat Suitability Index Models for the Lesser
Scaup (Wintering). A preliminary analysis of
the HEP model for the Lesser Scaup has been prepared to show benefits to one species in
the diving duck guild by increasing lower intertidal and deeper subtidal habitat. The Corps, in cooperation with the US Fish and
Wildlife Service, will also construct a With Project/Without Project comparison using
cover types as a proxy for habitat types and ecological guilds to demonstrate project
benefits in the feasibility report. These
analyses will illustrate the benefits of the project in a quantitative manner, and provide
backing to the qualitative assessment already provided.
The district agreed to make an earnest effort to provide additional habitat-based
evaluations for other species or guilds as presented for the lesser scaup in the district
response. Finally it was agreed that the
volume metric would be acceptable as the basis for in the incremental analysis of
alternatives
Action: The district will undertake a
habitat-based evaluation to quantitatively demonstrate ecological benefits associated with
the NER and LPP plans. An analysis of the HEP
model for the Lesser Scaup has been provided to show benefits to one species in the diving
duck guild by increasing lower intertidal and deeper subtidal habitat, but the district
will make an earnest effort to provide additional habitat-based evaluations for other
species or guilds similar to that developed for the lesser scaup. Finally, it was agreed that the volume metric
would be acceptable as the basis for in the incremental analysis of alternatives. The district will revise the draft report
accordingly to reflect information in the districts response and results of the
habitat based evaluation.
Comment: b. Incremental Cost Analysis (Attachment 4). The costs shown in this attachment do not coincide with the costs for the NER and LPP alternatives shown on pages 24 and 25 of the main report. Consequently, the conclusions of the ICA may not be valid. All costs shown in the report and attachments, appendices, etc., should be consistent.
District Response: Based on the ITR Plan Formulation Comments (shown below), the Incremental Cost Analysis (ICA) was redone taking account for additional costs such as the interest during construction (IDC). The total first cost of $66,156,000 is indeed correct; this figure plus the IDC ($12,914,000) results in the $79,070,000 used for the incremental cost analysis. The same can be said for the locally preferred plan.
There is no difference in the conclusions of the ICA whether one uses first costs or the total investment costs.
Discussion: The draft report and draft EIS will be revised to reflect the current incremental cost analysis.
Action: As indicated in the discussion.
Comment b - Part 2: Initial perusal of the ICA also shows that the
North and South Alternative would provide almost as much ecosystem
benefit while costing much less (based on the costs and benefits shown in the ICA
table) than the LPP. The district should
explain why the Federal government should cost share in a plan (the LPP) that costs over
$12 million more than the North and South Alternative but only provides ten percent more
benefits.
District Response: In accordance with ER
1105-2-100,
The National Ecosystem Restoration (NER) plan is one that reasonably maximizes ecosystem restoration benefits compared to costs, consistent with the Federal objective, shall be selected. The selected plan must be shown to be cost effective and justified to achieve the desired level of output.
Indeed,
there are diminishing returns in achieving higher outputs.
The difference in cost between the North and South (Seadrift) plan and the North,
Central (Riparian) and South (Seadrift) is large (approximately $30 million), but so too
are the difference in outputs (42 percent higher). This
equates to a small incremental cost increase, from $22.58 to $33.72 per unit. The final increment, the North, Central, and South
(Seadrift) alternative, does not appear to be reasonably justified since the additional
cost of $7 million results in a mere 0.4 percent increase in output.
Therefore, the agreed national
environmental restoration (NER) plan is the North, Central (Riparian) and South (Seadrift)
plan. With a first cost of $66 million, the
local sponsor indicated that this plan may be cost prohibitive with potential real estate
issues and political challenges needed to be met to implement the South
(Seadrift) alternative. They have since
identified two potential locally preferred plans (LPPs), the North, Central (Estuarine)and
South (No Seadrift) plan, with a first cost of $59 million, and the North, Central
(Riparian) and South (No Seadrift) plan with a first cost of $53 million. These LPPs did
not appear in the final array of alternatives, but were found to be cost effective during
the first iteration of the ICA.
For ecosystem restoration projects,
the non-federal sponsor is required to cover 35 percent of the NER projects
implementation costs. Since the locally preferred plan is a smaller-scaled version of the
NER plan, the same cost sharing formula should apply.
Discussion: The district noted that the ICA has
been revised to show the elimination of an additional plan in the first iteration of the
ICA, and a second figure has been added to show the incremental costs and benefits in the
final array of alternatives. However,
the analysis will need to be revised in accordance with the resolution of comment c. Seadrift
Lagoon Component below, that is the Seadrift Lagoon component should be excluded from
the NER plan.
Action: The
revised report will reflect the current ICA and exclusion of the Seadrift Lagoon component
from the NER plan.
Comment: c. Seadrift
Lagoon component. It is stated on page 24 of the main report that
due to real estate issues, potential real estate takings, and public
opposition that a consensus was reached by the Corps and the non-Federal sponsor to
exclude the Seadrift Lagoon component from the NER plan.
If this component is not implementable and is unacceptable to the local sponsor, it
should be considered as a planning constraint and be eliminated from all of the
alternatives. The study team should not waste
their time and funds investigating an option that is not implementable. The District should, however, note the
requirements contained in comment i(2), below, regarding real estate issues.
District Response: The Seadrift Lagoon component
was not removed from the NER. The meaning of
the statement quoted above (from page 24 of the AFB document) was that the Locally
Preferred Plan was derived from the NER, after excluding the Seadrift Lagoon component. That is, the NER remained the same, but because of
potential difficulties in implementing that
component, Marin County identified a plan (an LPP) that would be more likely to be
implementable by the local sponsor. That plan
was a derivation of the NER; essentially, the NER minus the Seadrift Lagoon component. In addition, a second LPP was identified. The second LPP is identical to the first LPP,
except for the Central alternative. One LPP
includes the Central (Estuarine) alternative, and the other LPP includes the Central
(Riparian) alternative.
Note: To clarify the discussions of the South
and South (Modified) alternatives, the names have been changed to more accurately reflect
the composition of both alternatives. South
is now South (Seadrift); South (Modified) is now South (No Seadrift).
Discussion: The
appropriateness of including the Seadrift Lagoon component in the NER plan was discussed. In addition to the non-Federal sponsor concerns
noted in the comment related to implementation and acceptability problems, Headquarters
staff advised that restoration of Seadrift Lagoon would not be considered appropriate for
ecosystem restoration under existing policy. Seadrift
Lagoon is a private man-made feature and would be considered enhancement. Because the Corps does not participate in
enhancement projects, federal cost-sharing participation could not be
justified for this component; therefore, the Seadrift Lagoon component must be excluded
from any tentatively identified NER plan. The
Seadrift Lagoon component may be implemented as part of an LPP, however, with 100% of the
associated incremental cost provided by the Non-Federal sponsor.
Action: The
draft report will be revised to exclude the Seadrift Lagoon component from the tentatively
identified NER plan.
District Response: As seen in response to comment g. Operations
and Maintenance (O&M) dredging, all tables of the AFB package have been updated to
include discussion of the South Modified [South (No Seadrift)] alternative. Since it is part of the tentatively selected LPP,
it will be analyzed fully like any other alternative.
Accordingly, discussion of the South (No Seadrift) alternative, and all of the
combinations it appears in, will be added to the text of the Feasibility report.
Note: Per a request by the Executive
Committee of the Bolinas Lagoon Ecosystem Restoration Study, the Central and Central
Modified alternatives have been renamed Central (Estuarine) and Central (Riparian),
respectively. The Central (Estuarine)
alternative emphasizes the importance of estuarine environment; that is, more
upland/riparian habitat is removed. The
Central (Riparian) alternative emphasizes the importance of riparian habitat; that is, no
riparian habitat is removed (less upland habitat is removed), and therefore less estuarine
habitat is created.
Discussion: As
discussed in comment c. above the Seadrift Lagoon component will be excluded from any
tentatively identified NER plan Concur with District response.
Action: The district will revise the draft feasibility
report and draft EIS will include the updated information related to the South (No
Seadrift) alternative.
Comment: e. Disposal
Costs at Hamilton Airfield Wetland Restoration site.
On page 22, (Disposal and Beneficial Reuse Sites) the report states that a
major assumption for disposal of material is
that certain costs for off-loading, piping, site management, operations and maintenance at
the Hamilton site will be Hamilton project costs, and not Bolinas Lagoon project costs. The table in Attachment 4 entitled "Bolinas
Lagoon Cost Summary" shows a column marked "Dredging/Disposal costs @
Hamilton". For the North, Central
(Modified) and South plan the Hamilton costs are listed as $33 million of a $66 million
first cost. It is not clear what part of the
Hamilton costs belong to Bolinas Lagoon. The
report needs to clearly state the basis for the assumption, and clarify what costs are
project costs. Also, see comment j, below, on this issue.
Comment: j. Relationship
between the Hamilton Airfield Wetland Restoration and the Bolinas Lagoon Restoration
Projects. Because of the effect on
Project Cooperation Agreement (PCA) language for the Hamilton Airfield Wetlands
Restoration project and calculation of costs and benefits for the Bolinas Lagoon project,
a clear understanding of cost allocation and other relationships between these two
projects is needed. The district should be
prepared to discuss this issue at the AFB or other meeting with HQUSACE prior to release
of a draft feasibility report for public review.
District Response e & j: One assumption used for cost
comparison of disposal sites is that the Hamilton Wetlands Restoration Project (HWRP)
would accept "clean" material removed from Bolinas Lagoon, whether dredged or
land-excavated, for beneficial re-use. To be
deemed clean, the material must be suitable for use as wetland cover. Another assumption used (and confirmatory testing
should verify) is that nearly all of the material to be removed from the Lagoon is not
only suitable for aquatic disposal, but also for use as wetland cover. The known exception to this is the material found
in Seadrift Lagoon, which is unsuitable as wetland cover.
We have assumed that the material in Seadrift Lagoon is suitable for aquatic
disposal because of the relatively low levels of copper sulfate previously measured. Thus, the costs shown in the AFB documentation
reflect all dredged material (wet material) going to Hamilton, all excavated material (dry
material) going to Hamilton (except that of Highway 1 fill removals), and any trees or
other vegetation going to Redwood Landfill.
All of the costs listed in the column
marked Dredging/Disposal Costs @ Hamilton are part of the Bolinas project
costs. In the AFB documentation, the dredging
and disposal costs were lumped together as one cost.
For the sake of clarity, the dredging and disposal costs will be listed in separate
columns in the feasibility report.
Discussion: Due to uncertainties surrounding the availability
of the Hamilton Wetlands Restoration Project (HWRP) or other alternative sites for dredged
material disposal from the Bolinas Lagoon ecosystem restoration project, the San Francisco
Deep Ocean Disposal Site (SFDODS) will be used as the disposal site for feasibility
evaluations. The costs associated with
disposing the dredged material at SFDODS are not expected to significantly impact either
the ICA or the NER/LPP determination. As HWRP
becomes more defined, and the uncertainties diminish, future ecosystem restoration
opportunities might be presented to allow material from the Bolinas Lagoon project to be
disposed of at HWRP. It is recognized that if
the HWRP or other alternative site is available and were to be used as the disposal site
for the Bolinas Lagoon project, any incremental costs above disposing the material at
SFDODS would have to be borne by that project.
Action: The
district will revise the draft feasibility report to reflect the uncertainty in the
availability in the HWRP and use of the SFDODS as the disposal site for dredge material. The draft report should recognized that if the
HWRP or other alternative site is available and were to be used as the disposal site for
the Bolinas Lagoon project dredged material, any incremental costs above disposing the
material at SFDODS would have to be borne by that project.
Comment: f. Least
cost disposal site. The district
needs to identify the least costly disposal site for the dredged material from Bolinas
Lagoon for the alternative plans. This is not
presented in the AFB materials. If, for
example, the SFDODS were the least cost disposal alternative the incremental costs of
transporting the material to the Hamilton Wetland Restoration site would need to be
determined. These incremental costs would
need to be justified by wetland restoration outputs at the Hamilton site, as was done in
the Oakland Harbor Deepening project.
District Response: As far as off-loading costs at the Hamilton site, we have assumed that the cost of the off-loader, piping, site management, and operations and maintenance at the HWRP will be paid for by the Hamilton project. For example, if these costs were not absorbed by the HWRP, aquatic disposal at the SFDODS would be the least-cost disposal alternative for all of Bolinas Lagoon, including Seadrift Lagoon. Adding the cost of the off-loader alone would preclude the use of the HWRP.
When the aforementioned assumptions were used to develop potential costs for the disposal of material removed from Bolinas Lagoon, the HWRP became the least-cost environmentally acceptable disposal alternative for all of the material, except that found in Seadrift Lagoon, which must be disposed of at the aquatic disposal site. It is noted that there may be limitations on the capacity for dredged material at HWRP, which may preclude the disposal of material from Bolinas Lagoon at that site. However, a PAC document will be completed to evaluate expanding the HWRP to include a new project increment, Bel Marin Keys, which is expected to alleviate concerns over capacity.
Discussion:
Contingent language regarding any
additional costs for use of the HWRP or other alternative disposal site for disposal of
dredged material from the Bolinas Lagoon ecosystem restoration project should be reflected
in the districts response on the potential use of the authorized HWRP. Also see discussion for comments e&j above.
Action: Due
to the above uncertainties involved with utilizing HWRP as a disposal site, SFDODS will be
used as the disposal site for feasibility evaluations. Also see Action for comments
e&j above
Comment: g. Operations and Maintenance
(O&M) dredging.
The main report states that the Bolinas Lagoon Ecosystem Restoration project would
be a one-time effort, because maintenance dredging is prohibited in the lagoon
by the Gulf of the Farallones National Marine Sanctuary.
If maintenance dredging is prohibited, no matter how infrequent, then why would a
one-time dredging effort of over 1.5 million cubic yards of sediment from the
lagoon be permitted? The district should
provide an assessment of what the lagoon will look like over a longer period than the 50
years used in Attachment 3 to show the historical and projected volumes. While the period of analysis is 50 years for
purposes of economic evaluation, the life of the project is assumed to be indefinite for
ecosystem restoration. Such an assessment and
evaluation should also examine the desirability of spending over $50 million dollars and
then letting the lagoon gradually fill in with sediments until it is the same as
todays condition. The Principles and
Guidelines and ER 1105-2-100 specifically state that plans may be formulated which
require changes in existing statutes, administrative regulations, and established common
law
The report should examine the
frequency needed to conduct maintenance dredging so that the depths obtained during the
initial construction are maintained over the life of the project to assure that project
benefits are maintained. The requirements of
periodic dredging for all alternatives should be examined to identify the proper NER and
LPP plans.
District Response:
The Bolinas
Lagoon Restoration Project is attempting to restore an ecological and geological system
that was altered by human mismanagement. Lagoon
systems and shallow water estuaries are typically transient settings that normally
progress from fully functional tidal systems to meadows.
However, in the case of Bolinas Lagoon, this process is periodically interrupted by
seismic activity that dramatically increases tidal prism by physically dropping the lagoon
bottom elevation and liquefying the sediment (this occurred in the 1906 earthquake). In a study performed for the USGS, it was found
that there is considerable evidence that significant earthquakes occur along the San
Andreas Fault in this region at a regular interval of three to four hundred years. It is believed that this process has kept Bolinas
Lagoon open for far longer than a typical lagoon system, and it is strongly suspected that
it would have stayed open even longer if humans had not disrupted the lagoon and its
watershed.
Looking at
numerous studies pertaining to the lagoon, lagoon maps/bathymetries, and aerial photos,
the Corps believes the lagoon has been filling in over the last 100 to 150 years at
approximately 3 times its normal rate. This
is an average rate since there were most likely times of super elevated sediment input
alternating with near normal input rates as a result of varying land management practices. This overload of sediment has sped up the lagoons
transformation process to the point where inlet closure could occur as soon as 2050. This would change the system, increasing the rate
of meadow formation. Current opinion is that
if the lagoon were left on its own, by the time the next earthquake hit the lagoon, it
would be too far into the meadow formation processes to be significantly reversed.
Given the
situation described above, the County of Marin (local sponsor) and the San Francisco
District would ideally like to restore this system to its stable
condition, which is a lagoon that progresses through the normal phases of a
lagoon, set back periodically by natural processes.
Although regular maintenance, such as regularly scheduled dredging every ten years
for example, does not correspond with the project goals, there may be an occasion in the
future when it is necessary to perform work after the project is physically completed in
order to ensure that the benefits of this project are being realized. The Feasibility Report will include a plan to
ensure that the project goals, as intended, are reasonably being achieved. For example, If A occurs, than B & C
will need to be done. If K occurs than
nothing will need to be done. If M occurs we
will have to take N action within XX months. Because
the lagoon is strictly regulated by the Gulf of the Farallones National Marine Sanctuary,
all work in the lagoon must be approved through the permit process of the Sanctuary. Future dredging would only be allowed for
scientific or ecological purposes, i.e., for the purpose of restoration.
The Corps
will cost share the construction phase of the project, as well as the monitoring and
adaptive management program for up to five years after the excavation work is completed. Any work after the five-year period, be it
monitoring, adaptive management, dredging, etc., will be the responsibility of the local
sponsor. Cost-sharing responsibilities of
Marin County and the Corps will be described in more detail in the Operation, Maintenance,
Repair, Replacement and Rehabilitation (OMRR&R) plan of the feasibility report. Specific cost-sharing responsibilities will be
negotiated and later incorporated into the language of the project cost-sharing agreement
(PCA) before construction.
The lagoons physical condition and habitats were projected 50 years into the future to meet the typical Corps period of analysis for the purpose of benefits/costs analyses, according to Planning Manual (IWR Report 96-R-21) PGL-96-01 and PGN ER-1105-2-100, Appendix D. This was accomplished using the projected infilling rate and the available data from 1968 to 1998. With the annual infilling rate projected, the loss of lagoon volume and potential tidal prism was calculated by subtracting the annual rate from the 1998 value. The projection of potential tidal prism was used to estimate the inlet closure date using the OBrien Criteria (Table 1). The results of this projection showed the inlet could close in the year 2050, given the right conditions.
Table
1. Without Project Inlet Closure Estimation
![]() |
power versus wave power.
Using this same analysis, the inlet closure was calculated for each alternative and projected 50 years into the future (post construction - assumed 2008) by using the new lagoon potential tidal prism as a starting point and subtracting the estimated annual sedimentation rate from it. The inlet closure estimates are provided for the NER plan (North, Central (Riparian), and South), the two runners up, and the two LPPs (North, Central (Estuarine), and South (No Seadrift) and North, Central (Riparian), and South (No Seadrift) (Tables 2 through 6).
Table 2. North, Central (Estuarine), and South (Seadrift) Alternative Inlet Closure Estimation
![]() |
*Inlet closure is estimated to occur at a closure index of 15. The closure index is essentially a ratio of tidal power versus wave power.
Table 3. North, Central (Riparian), and South (Seadrift) Alternative Inlet Closure Estimation
*Inlet closure is estimated to occur at a closure index of 15. The closure index is essentially a ratio of tidal power versus wave power.
![]() |
Table 4. North, Central
(Estuarine), and South (No Seadrift) Alternative Inlet Closure Estimation
![]() |
*Inlet closure is estimated to occur at a closure index of 15. The closure index is essentially a ratio of tidal
power versus wave power.
Table 5. North, Central (Riparian), and South (No Seadrift) Alternative Inlet Closure Estimation
![]() |
*Inlet closure is estimated to occur at a
closure index of 15. The closure index is
essentially a ratio of tidal power versus wave power.
Table 6. North and South
(Seadrift) Alternative Inlet Closure Estimation
![]() |
*Inlet closure is estimated to occur at a closure index of 15. The closure index is essentially a ratio of tidal power versus wave power.
Tables 1
through 6 illustrate that if any of the alternative plans were constructed, the inlet
closure index for the year 2050 would be lower than that of the without project condition
(given the existing data and no major alterations to the system).
In addition
to the inlet closure condition, the lagoon habitat was projected for both with and without
project conditions. This was difficult to do
since there were no mathematical models available, and numerical modeling would have been
very expensive and time consuming, and would have provided limited information beyond ten
years (or less).
We decided,
therefore, that the best approach would be to use the lagoon data from the past 30 years
as a model of the system. It was estimated
that for a given lagoon volume or tidal prism, there would be a certain amount of upland,
intertidal, and subtidal habitat. This was
based on the same physics as lagoon inlets, which says that the dimensions of an inlet are
based on the tidal prism of a system. As
tidal prism increases, the flow through the inlet widens the inlet, and as tidal prism
decreases, the inlet dimensions decrease. Essentially,
for a lagoon system with a particular potential tidal prism or energy state,
there is a given equilibrium state that the lagoon can reach as long as there is adequate
time for the system to adjust to the inputs. There
are currently no studies that directly pertain to lagoon systems to support this
methodology, but the use of historical data and like systems to determine what a given
system would look like given a set of physical inputs is a documented technique in stream
restoration. In a sense, the lagoon data has
provided a calibrated model of itself. Since
the restoration alternatives were designed using historical data, and essentially followed
the timeline of the lagoon backwards, this seemed to be a reasonable assumption.
The problem
with this method is that once the lagoon volume falls outside of the historical lagoon
volumes, the habitats quantities are extrapolated from the data instead of interpolated
from the data, which potentially extends or proliferates an inaccurate trend. This was the case in determining the without
project condition (which was entirely extrapolated) and the with-project condition
(extrapolated for some post construction levels since lagoon volume was greater than
highest level recorded). Tables 7 through 13
provide the habitat data for the historical conditions, without project conditions, and
with project conditions. The lagoon volume
following construction was determined by subtracting the annual sedimentation rate from
the post-construction volume. This may
introduce more inaccuracies, however, since the sedimentation rate may drop due to an
increase in flushing efficiency.
Table 7. Historical
Habitat Levels (measured from bathymetries and water level data)
![]() |
![]() |
Table
8. Without Project Habitat Projections
Table 9. North, Central (Estuarine), and South (Seadrift) Alternative Habitat Projection
![]() |
![]() |
Table
10. North, Central (Riparian), and South (Seadrift) Alternative Habitat Projection
![]() |
Table
11. North, Central (Estuarine), and South (No Seadrift) Alternative Habitat Projection
Table 12. North, Central (Riparian), and South (No Seadrift) Alternative Habitat Projection
![]() |
Table 13. North and South (Seadrift) Alternative Habitat Projection
![]() |
As seen in
Tables 7 through 13, all of the top alternatives and potential locally preferred plans
will lead to a lagoon volume/habitat level that is higher than the 1998 condition in the
year 2058.
Projection
of this type of data beyond the year 2058 is strongly discouraged since the data becomes
over extended (extension to 2058 for with project is an overextension of data itself). The shortcoming of using extrapolated lagoon
volume/habitat levels, the uncertainty in the sedimentation rate and other factors make
setting hard numbers very risky. However,
some idea of what will happen can be provided using this information to give an idea of
what the distant future (100 to 200 years) may hold.
For the NER plan (North, Central (Riparian), and South), the lagoon will not look
like the 1998 condition until 100 years after construction, and inlet closure would not be
a factor until 130 years following construction. For
the LPP plans, the time frame is in 80 years the lagoon will look like the 1998 condition,
and it will be 110 years before the inlet closure is a factor. Once again, the numbers must be used in the
context that they are provided (that is, a rough long-term estimate based on numerous
assumptions and limited data).
Using this
information, it should be noted that even the largest project (the NER) will probably not
open the lagoon enough or restore the system to the point of keeping it open until the
next earthquake. Since closure can begin in
2140 (assuming 2008 construction), the next earthquake may not come until the year 2200 or
beyond (300 years plus 1906 earthquake). This
expected level of performance is based on the best available information.
Discussion: The non-Federal OMRR&R project
requirements were discussed. The non-Federal sponsor understands they be responsible for
OMRR&R of the project for so long as the project remains authorized. Although regular maintenance dredging is not
anticipated, such as regularly scheduled dredging every ten years for example, it was
recognized that there may be an occasion in the future when it becomes necessary to
perform work after the project is physically completed in order to ensure that the
benefits of this project are being realized. The
Feasibility Report will include a plan to ensure that the project goals, as intended, are
reasonably being achieved.
Action: The district will revise the draft
feasibility report to include the above discussion, and in accordance with the comment c.,
the tentatively identified NER plan will be modified to exclude the Seadrift Lagoon
component.
Comment h.
Operations,
Maintenance, Repair, Rehabilitation and Replacement (OMRR&R). The District should identify the entire range of
potential OMRR&R activities (including prevention of encroachments), not just future
dredging, for the various alternatives.
District Response:
OMRR&R activities for the project would include any monitoring, adaptive
management and dredging activities occurring after the close of the construction period,
which would occur five years after all scheduled excavation work had ceased in the lagoon. Real estate rights, including land easements and
the acquisition of permanent interests in the project lands, may be other OMRR&R
responsibilities of the local sponsor. The
details of the real estate responsibilities and OMRR&R costs of the local sponsor have
yet to be determined, but will be part of the Real Estate Plan and the OMRR&R plan in
the feasibility report.
Discussion: In addition to the OMRR&R items
discussed in the district response, the draft feasibility report will need to address
project monitoring and adaptive management activities.
The draft report will need to clarify the proposed five year monitoring and
adaptive management activities to be accomplished as part of construction, i.e. included
in total project costs and cost shared accordingly, and those activities to be
accomplished at full non-Federal expense as part of OMRR&R. It was recognized that it may be conceivable that
a functional portion of the project may be turned over to the non-Federal sponsor for
OMRR&R while the proposed cost shared monitoring and adaptive activities are being
accomplished.
Action: The draft feasibility report will clearly
identify the nature, extent and cost of monitoring and adaptive management actives to be
accomplished and cost shared as part of construction, and
extent and cost of required OMRR&R activities to be accomplished at full
non-Federal expense.
Comment i. Real
Estate.
Comment (1):
When OMRR&R responsibilities attach to a project, such responsibilities usually
last for so long as the project remains authorized. Conversely,
if the non-Federal sponsor has no OMRR&R duty, the project effort would be limited to
the period of construction. Whether an
OMRR&R duty attaches is one key to determining the duration of required real estate
interests. Accordingly, the District should
be prepared to discuss the duration of required real estate interests during the AFB. Moreover, if an OMRR&R duty will apply to this
ecosystem restoration project, the District should justify all interests less than fee
during the AFB discussions. Finally, the
District must explain why [t]here are no expected costs associated with LERRDs for
the non-Federal Sponsor if the proposed LPP is implemented (see p.25).
District Response: Real estate rights obtained by the
Non-Federal Sponsor (NFS) in perpetuity are considered necessary for this project, whether
or not they are determined to be OMRR&R responsibilities. The acquisition of permanent interests in the
project lands for the entire range of potential OMRR&R activities, such as prevention
of encroachments (as stated in comment h) are considered necessary to protect the purpose
of the project. There are issues, however,
as to what estates, non-standard versus standard, that can be used and various types of
ownerships. The standard estate for permanent land rights to be acquired
for an ecosystem project is fee. Due
to the types of ownerships, nature of the lands involved, and existing laws regulating the
lagoon, the approval of a non-standard estate of a permanent easement will be requested. Such language easement is presently being
prepared. Following is more information
on this:
Estates Private Ownerships
There are approximately 52 privately owned parcels, in addition to a few parcels
owned by the Marin County Junior College, Sanitary District No. 3, Stinson Beach County
Water District, and the Seadrift Association. Most
of these lands are submerged lands in the Bolinas Lagoon.
A permanent easement for dredging (one-time) and for the restriction of any
property owner to do anything that would interfere with this project is considered
sufficient. This lesser estate rather than
fee would be the preferred estate due to the NFSs concern of difficult and costly
acquisitions. Further, consideration must be
given to the rules and regulations regarding ANY activity in Bolinas Lagoon. The Bolinas Lagoon is closely and strictly
governed by the Point Reyes/Farallon Islands National Marine Sanctuary. Section 922.82 of 15 CFR Ch. IX (1-1-97 Edition),
which regulates all activities in the Bolinas Lagoon.
Any activities, such as exploring for, developing and producing oil or
gas
discharging or depositing any material or other matter
construction of any
structure other than a navigational aid, drilling through the seabed, any disturbance to
seabirds or marine mammals
and removing or damaging any historical or cultural
resource is strictly prohibited by their laws. The
National Marine Sanctuary also has strict permitting requirements for anything they would
allow to be done in the Bolinas Lagoon. Considering
the strict permitting requirements and regulations already governing the Bolinas Lagoon,
to include privately owned lands in the Bolinas Lagoon, the required lands for the
proposed ecosystem project are already protected from any use that would interfere and/or
violate the integrity of the project or the projects purpose. The easement language currently being considered
would provide the additional guarantee of use of the required lands for the projects
purpose and would supplement the already existing restrictions enforced by the National
Marine Sanctuary.
Estates Lands Owned by Marin County
The majority of the submerged lands in the Bolinas Lagoon required for this project
consist of approximately 307 acres. Marin
County was granted these lands through legislation in 1969, from the State Lands
Commission (SLC). This grant provided them
with sufficient rights to provide these lands for the purposes of this project, in which
the SLC concurs. Marin County, however, is
NOT the NFS, but is part of the same political body of which the sponsor also is, i.e.,
the same representatives sit on the Board for both. The
sponsor can elaborate on the exact legal relationship between them and Marin County during
the AFB. The issue is how does the NFS (Marin
Open Space District) legally provide the lands, if they are legally held by Marin County,
to satisfy the requirements of the PCA. A
Memorandum of Understanding (MOU) will be executed between Marin County and the Marin
County Open Space District. The main purpose
of the MOU would be to provide for Marin County allowing the Marin County Open Space
District to use these lands in perpetuity for the project.
The fact that the non-Federal sponsor is providing the lands in the Bolinas Lagoon
via an MOU with Marin County, with Marin County retaining the ownership
granted to them by the State Lands Commission, and the fact that the Marin County will
not, if fact, have to purchase/acquire these lands, will preclude the sponsor from
receiving LERRDs credit for such submerged lands. The
SPN real estate representative will coordinate with the non-Federal sponsor in more detail
with regard to the crediting of LERRDs and provide them with the PCA clauses regarding
LERRDs for further discussion and communication to assure a mutual understanding of the
crediting of LERRDS.
Estates Federally Owned Lands (GGNRA) and State-Owned Lands (California
Department of Transportation)
The rights to a few small areas of submerged lands in Bolinas Lagoon would have to
be obtained from the U.S. and the State of California.
These will probably require non-standard estates as well, but still needs further
investigation.
Regarding the statement in paragraph (1) (last sentence) that says requests an explanation of no expected costs associated with LERRDs
This is incorrect. There will be LERRDs costs for easements and associated administrative costs to acquire such. The total LERRDs costs and associated administrative costs are expected to be $4-6 million.
Comment (2): Although the AFB documentation
mentions a concern regarding costly takings claims if the NER Plan is implemented, no
analysis is provided as to the basis for this concern.
The District should be prepared to discuss this issue in depth during the AFB with
an expectation of follow-on reporting responsibilities to facilitate a decision prior to
release of the draft report for public review.
District Response (2): An investigation as to a taking in the Seadrift
Lagoon (included in the original NER Plan) was done by the Appraisal Branch and the Real
Estate attorney. The conclusion was that
there is not a taking, but the attorney concluded there is a high probability
that there will be numerous lawsuits that would receive merit in Court. The NFS can support this from their experience and
insight into such issues with these landowners in the project area.
Discussion:
Coordination should be undertaken with the sponsor to identify and resolve real
estate issues so that a comprehensive REP can be included in the draft and final reports.
Outstanding issues include the nature of the perpetual easement that will be proposed for
use for this project and the type and details of the proposed agreement between the
Sponsor and Marin County.
Action: Following
coordination and consultation with the Sponsor, the District must prepare a comprehensive
REP prepared in accordance with paragraph 12-16 of ER 405-1-12 for inclusion in the draft
and final reports. Because consensus was
reached that the Seadrift Lagoon component will not be part of the proposed project, the
report (including the REP) should not discuss takings or other acquisition issues
pertaining to the Seadrift Lagoon component. Regarding
the nature of the perpetual interests that must be acquired to support implementation of
the project, the draft REP discussion should note that fee is the standard interest
required to support implementation of ecosystem restoration and other environmental
projects. However, given the circumstances of
this proposed project, the REP should also indicate that perpetual interests less than fee
(for example, perpetual easement interests) may be sufficient to implement the project and
that, following refinement of the project and real estate acquisition plans, final
determination will occur on the nature and extent of the required real property interests. Finally, if the real estate cost estimate was
based on provision of fee by the Sponsor, the REP should indicate that such estimate is
for planning purposes and that the value and credit amounts may be less if less than fee
is determined to be required to support the project.
Comment: k.
Watershed influences. The report
does not cover in any depth the nature and scope of studies underway to address upland
watershed measures to reduce sediment inflows to Bolinas Lagoon. As this upland source of sediments is the primary
cause of the sedimentation problems in Bolinas Lagoon, such measures should be closely
examined to assess their effectiveness in reducing the amount of sedimentation. The effectiveness of these measures would have a
considerable bearing on the necessity and amount of any future O&M dredging that would
be needed to assure that the benefits from the ecosystem restoration project are available
throughout the life of the project.
District Response:
A discussion of the nature and scope of the watershed studies will be
added to the Draft Feasibility text, including a synopsis of the conclusions and
recommendations (that were provided to the Corps by the contractor in August 2001). In addition, the complete watershed study will be
attached to the Draft EIS/R as an appendix. An
excerpt from the introduction of the watershed study (nature and scope) and a summary of
the information in the Conclusions section (conclusions and recommendations) are provided
for clarification to address the concerns in the above comments.
The nature
and scope of the studies are described on pages 1-1 and 1-2 of the watershed study
introduction as follows:
U.S. Army Corps of Engineers
(USACE) commissioned the Bolinas Lagoon Watershed Study to evaluate the sources and
magnitude of sediment delivered to the lagoon via erosional processes within the
watershed. Though there are several potential
sources of sediment to the lagoon, including tidal transport and windborne deposition,
this study focuses on the watershed sources. A
copious literature review was conducted to determine sediment transport rates from wind,
tidal, and watershed sources that had been established in previous studies. Historical land use data was collected and used to
establish correlation with rates reported in the literature. Land use history of the watershed and the results
of our reviews are presented in Section 2. Extensive
field surveys of the watershed were conducted to capture a representative sample of mass
wasting mechanisms throughout the watershed. Both
qualitative and quantitative information about landslides, earthflows, gullies, and road
related erosion was collected and used together with regional values for soil creep and
stream bank erosion to create an account of relative significance of each. Field survey data was fed into a basic mass
wasting mathematical model, which was used to normalize the data and produce the resulting
annual sediment input rates. These data,
calculations, and results were checked against land use history and previous studies of
the lagoon, as well as literature values for similar watersheds, to establish the
reliability of the results.
The following conclusions and recommendations were provided in Section 6 (Conclusions) of the watershed study:
1. Bolinas Lagoon was never a deep embayment, although it may be shallower now than it was 150 years ago.
2. Although historic land management activities (like timber harvest for lumber and firewood, mining, and ranching) increased erosion rates in the past, current erosion rates appear close to background rates. Current land management is minimal; most of the watershed area is parkland with limited uses.
3. It is unlikely that any changes to management practices within the watershed would have a significant effect on sedimentation rates within the lagoon.
4. Most of the sediment entering the lagoon via the watershed is derived from natural mass wasting, and is an order of magnitude less than the potential volume mobilized by the tide.
5. One area that could be restored to help reduce even further the amount of sediment entering the lagoon would be at Pine Gulch Creek. Restoration of the lower reach, where it is currently diked, could reduce the amount of fine sediment transported into the lagoon by allowing it to deposit on the floodplain instead.
Future projects in the watershed would not significantly affect sedimentation rates within the lagoon, but could focus on habitat restoration as its goal (possibly under the Continuing Authorities Program). Habitat/aquatic restoration would be especially effective at the lower reaches of the surrounding streams, which are currently channelized. Because sedimentation rates from the watershed appear to have recovered from past land management practices, O&M activities in the lagoon if any were to be conducted would not be significantly influenced by the amount of sediment coming from the watershed.
Discussion: The draft feasibility report will be revised to reflect this information
Action: As indicated in the discussion.